Construction Contract Risk Allocation – What You Don’t Know Can Hurt You

Posted by Mark E. Alpert, PE, DBIA, WDBC Executive Director on Fri, Jan 19, 2018 @ 01:26 PM

construction-contract-risk-allocationThe underlying principle of allocating and managing risk in projects using CMAR or design-build delivery methods is to embark upon a collaborative process between the owner and construction professionals with initial discussions on how to allocate specific risks to the party best positioned to manage and assume the risk. Chapter 3 of the WDBC Water and Wastewater Design-Build Handbook, Fourth Edition, Apportioning and Managing Project Risk, is an excellent resource on the subject of risk in collaborative delivery projects. However, the purpose of providing this more specific commentary is to share some of the risk allocating scenarios observed during the contractual process.


Download the 4th Edition of the Water and Wastewater Design-Build Handbook.

Get My Copy Now


An important example of this situation is one that occurs when owners make initial and uninformed decisions to transfer most project risks to the construction professionals, without a collaborative process. While generally well-intended, often these initial risk-shifting decisions may actually harm the owner’s project. Consequently, this can decrease interest in the project from highly qualified construction professionals. At any given time, construction professionals are pursuing numerous project opportunities with limited resources. These high-risk projects often exceed a construction firm’s risk capability and, subsequently, they pass on those projects and pursue more risk-balanced opportunities instead. Added to this scenario is the misperception that “contractors do not manage risk, they price it,” which is not accurate. Owners transferring a significant portion of project risks to construction professionals often face the potential of increased project contingencies and premiums for bonding and insurance. No owner wants to pay more for their project, but that is often an unintended consequence of these initial decisions.

Provided below are a few risk allocation scenarios that owners and industry professionals encounter in developing project contracts. A second blog will follow with other contractual areas that include risk.

Custom-Tailored Contracts.

Often when owners write their own contracts, they are derived from those used for older design-bid-build projects. Because they are not collaborative based, these types of contracts inevitably shift an imbalance of risk to the construction professionals. The allocation of risk is a negotiated discussion, which has been modeled in several excellent industry-standard construction contracts available for the collaborative delivery of water and wastewater projects. These standard agreements were meticulously developed by teams of owners, engineers, construction managers, and design-build firms, and are fair and risk-balanced.

Edited Industry-Standard Contracts.

Since no two projects are alike, it is not uncommon for standard contracts to require minor edits to accommodate the job. But often significant edits and deletion of key provisions in standard contracts are not always to the benefit of the owner in terms of risk and must be part of the discussion in finalizing the contract. Owners providing a copy of a “draft contract” within the RFP initiate the discussion process for risk allocation, which begins the collaborative relationship that achieves agreement in the management process.

Shortened Notice Requirements.

Another area in risk allocation focuses on the “identified notice requirements” within a contract. When notice requirements are drastically reduced in the contract (e.g., from 14 days to 5 days), this action results in significantly limiting the firm’s ability to file a legitimate claim or request an equitable adjustment in contract cost and/or contract time.

Unilateral Change Order Provisions.

While many projects encounter some change orders, in the discussion of risk allocation, these actions should be bilateral -- meaning they should be mutually agreeable to both the owner and the construction firm. This topic is also an important one to address in the collaborative process.

The solution to these situations is fundamentally easy. Use industry-standard documents, and follow the industry-standard recommendations on risk allocation and management. CMAR and design-build projects are built upon collaboration, mutual trust, appropriate risk-sharing, and openness. Owners benefit from this collaborative process of risk allocation in developing their contracts – and ultimately achieve a successful project and relationship.

WDBC Executive Director Mark Alpert is a former CH2M senior vice president for design-build (Denver, CO), WDBC founding member and past president. For more than 35 years, Mark has been a pioneer in the development of integrated project delivery for water and wastewater projects. Even before the term “design-build” was commonly recognized, Mark was focusing on cost-effective design and construction, which led to the formalization of design-build and other collaborative project delivery methods.